Southern California Healthcare Construction Executive
Review; 2000.
Cedars-Sinai Research II
Kenneth Orgel, manager of
construction for Cedars-Sinai Medical Center, is pleased with the
progress of the as yet unnamed research II building.
The existing research area, called the Cedars-Sinai Davis
building, was completed in 1992. The second phase of the Los Angeles
research structure will include a total of 70,000 square feet,
making for a total of 220,000 square feet dedicated to research.
"The whole project has spanned more than 10 years,"
Art Border, AIA, project architect for RBB Architects, Inc. He added that
Phase II planning began in December 1997.
There was a building already located where Phase II is. That’s why the
building had to be built incrementally, he added. The original building,
damaged beyond repair by the Northridge earthquakes of 1994, was torn down
in 1998, with the assistance of a small FEMA pledge toward reconstruction.
Research II’s construction was planned to begin in 1994. Border
explained things changed and that the impetus for the revised project was
the Northridge earthquake as well as subsequent changes in technology due
to problems with welding procedures observed after the earthquake.
Once that was done, the project moved forward quickly, according to
Border.
After exploring all the available possibilities, he said, "We
introduced new joint technology to the second phase. This is one of the
easier ones to implement. We changed the grade of steel to ensure improved
welding characteristics."
The construction of Research II began on April 26, 1999, Orgel said.
October 2000 is when the building will open, he added.
"When the building was
designed originally, most of the components were designed in Phase
I, including an emergency generator capacity, electrical
substations, core support functions, as well as utilizing existing
vertical elevators and stairwell enclosures," he said.
"The building includes an extensive ground floor laser
laboratory, medical research labs and two floors of comparative
medicine," Orgel said. Major equipment added to this new phase
includes optic labs and spectroscopy labs containing spectrometers,
fume hoods and space for procedure tables.
"Also, a research facility is typically a large energy consumer,
one of the reasons being the need to utilize 100 percent outside
air," Orgel said. "This air is moved across cooling coils to achieve
the desired interior temperatures and by utilizing VAV [variable air
volume] components. We apply appropriate diversities and the loss of
conditioned air is minimized.
"The most significant evolution from Phase I to Phase II I
addressing medical researchers’ needs and bringing the data and
computers right to the work bench," he said. "Basically, it’s
biomedical research, which benefits not only our community, but the
world community to research the detection, diagnosis, prevention and
treatment of disease. We are doing research in neurosurgery, brain
tumors, inflammatory bowel disease, medical genetics, cancer and
endocrine diseases."
Total costs for the second phase are estimated at $33 million.
Jason Groshart, project manager for Peck/Jones Construction
Corporation, the general contractor for the Research II project,
said it’s an eight-story structure.
Problems encountered thus far include traffic problems while
unloading materials. "It’s one of the tightest job sites I’ve ever
seen," Groshart said. "It’s all been a challenge actually."
Congratulations
Cedars-Sinai Research II
for making a difference
in our
community
BERGELECTRIC
CORPORATION
Electrical
Contractors Electrical contractors
specializing in large-scale
commercial,
industrial and
manufacturing projects
GIROUX
GLASS, INC.
Glass, Glazing,
Architectural Metals Nationally recognized
glass subcontractor for
new construction,
high-rise
renovations
PACIFIC WEST
MECHANICAL, INC.
Plumbing &
Piping Medical, industrial and
commercial
piping--
performed to the highest
standards
REBAR
ENGINEERING, INC.
Reinforcing
Steel
Subcontractor Furnish, fabricate and
install
reinforcing steel, wire mesh
and post
tension cables
WESTERN AIR &
REFRIGERATION CO.
Mechanical Contractors Providing
comprehensive
mechanical construction
services
According to Orgel and
Groshart, chief among those challenges is the fact that
approximately 300 researchers are working in Phase I, the
Cedars-Sinai Davis Research Building during the construction.
"We need to ensure we control vibration, noise and other
obstacles without compromising life safety systems or the work of
the researchers," Orgel explained. "In order to mitigate vibration
that would impede delicate experiments, a rigid short-span steel
frame was incorporated."
Groshart added, "Keeping the researchers happy and keeping their labs
functional while performing a major construction job has been, without a
doubt, the biggest challenge."
Orgel said the two phases will form a contiguous structure, connected
in 64 locations, "as opposed to a separate structure with an expansion
joint.
"This project integrates steel moment resisting steel frames from two
different generations of joint technology," Orgel said. "We have
successfully integrated both structures."
Border said Phase I was designed to receive Phase II. "It’s physically
glued to the structural system in Phase I," he said. "All vertical
transportation and stair towers are already resident in Phase I."
What he finds unique about this project is the fact the construction
team is "trying to take a difficult site and get maximum use out of it."
"[The project] integrates the existing Cedars-Sinai exterior design
vocabularies as well as that of the first phase," Orgel added. "It blends
well, giving an overall compatible feel."
Border said about 23,000 square feet is dedicated to generic
laboratories. Two floors, roughly totaling 15,700 square feet, are set
aside for comparative medicine. The laser lab is the only specialized lab
in the building and will operate on the ground floor. Support areas total
about 11,000 square feet.
Cedars-Sinai
hopes to attract corporate clients to the fourth and fifth floors, in a
kind of corporate partnership with private sector research. This would
allow the hospital to fully build out the building, while generating
income from tenants until all of its space is needed for Cedars-Sinai
research.
Inside, lab details include necessary flexibility, Border said.
"The goal was to propagate generic laboratory modules, much like we had
in Phase I, which shared core support areas," he added. "Because research
programs are changing during grant durations, they’re highly volatile over
time. We took the developed Phase I concept and tried to enhance on it in
a number of ways."
Some of those included additional adjustment in bench areas, in
overhead shelving and in making bench tops adjustable to varying heights.
Benches can be broken down and removed completely.
"A significant difference between Phases I and II included an increased
need for data communication at the desktop," Border said. This is intended
to "respond to the increasing use of computer data applications at the
work bench."
The use of mobile pedestals allows for the reconfiguration of lab
space. In research areas you can even break down a workbench aisle if
needed.
"It’s completely flexible to the maximum extent that’s possible in a
lab environment," Border said.
The first part of this phased construction included demolition of the
basement of the original building on the site and clearing utilities for
the new infrastructure. Next up was the shell and core package and
accompanying design changes to meet code revisions. Finally, that allowed
for the tenant development to catch up with the rest of the package. The
contract was a negotiated process with Peck/Jones.
"That allowed for a tremendous amount of collaboration from the owners,
and gave us as architects, I think, much better control than a stipulated
lump-sum competitive bid," Border said. Accepting FEMA funds meant a
competitive bid process was required.
In addition, Border said, there was "persistent value engineering
throughout the process."
When constructing a project of this scope, working together is
essential.
"It’s been a pleasure to do this job," Groshart said. "We are a team.
We’re all in it together."
"This job is truly unique in that everyone gets along and works for the
common good of the project."
If a problem is discovered during construction, Groshart added, there’s
no finger-pointing or trying to say it’s someone’s fault. Team members
just work together to solve it.
The team process has included "a lot of value engineering," he said. At
the beginning of the project, each subcontractor was asked, "What can we
do to save everybody money?"
"The quality is the same," Groshart added. "It’s a different brand."
All this, and they’re still on schedule too.
"It’s a fantastic project," Groshart said. "Not only is it going to
expand the research capacity of the hospital, but it’s just been a great
project to work on."
Border took praise a step further. "The project thus far is, I think,
one of the smoothest running we’ve done with this client," he said. "It’s
the best partnering team that we’ve ever assembled."
Orgel agrees the team process has been a huge success.
"The success of this project is primarily due to the excellent team
that we established for the construction of the second phase," Orgel said.
Some key team members included William Driver of Peck/Jones, Border and Ed
Saborio of Planning Partners, Ltd.
"In the 14 years I’ve worked here, this is the best team I’ve had," he
added. "Additionally, the user groups, headed by Dr. Shiomo Melmed
[director of the Cedars-Sinai Research Institute], were outstanding. They
have worked with us every step of the way and this has proved to be
invaluable. Everybody is so well-focused. We have an excellent contractor,
a world-class architect, and extremely participatory user group. When you
combine these elements, the degree of success increases significantly."
FACTS& FIGURES
Name: Cedar-Sinai Research II
Location: Los Angeles
Owner: Cedars-Sinai Medical Center
Type of Project: New construction of an eight-story
research facility
Architect: RBB Architects, Inc., Los Angeles
General
Contractor: Peck/Jones Construction Corporation, Los Angeles
Size: 70,000 square feet.
Cost: $33 million
Construction Time: Actual construction began April 26,
1999. Some site work/demolition started in 1998. The projected
completion/occupancy date i October
2000.